Sierra Pacific Industries Announces New Sawmills

 

Sierra Pacific Industries (SPI) plans to build a new sawmill complex, including two new sawmills located adjacent each other on the east side of its existing site in Eugene, Ore., eventually operating under one roof and ultimately replacing the existing sawmilling facilities.

The two sawmills will include a stud mill, patterned after SPI’s mill in Shelton, Wash. and consuming logs 5-16 in. diameter, and a cutting mill (large log mill) that will process logs 16 in. and larger.

The log mix will be similar to the current mix; however, the cutting mill is designed to extract greater value from each log, including dimension lumber, rough and surfaced timbers, shop, VG, clears, etc.—designed similarly to SPI’s four cutting mills in California.

The location allows SPI to complete the construction off-line while continuing to run its three existing facilities and maintain full employment of more than 300, before moving into the new facilities as they are completed.

The new sawmill complex will become one of the largest single site lumber producers in the U.S with an annual production capacity of 650MMBF, compared with the existing capacity at Eugene of more than 350MMBF.

The new sawmill project timeline anticipates completion between 2025 and 2026, contingent on securing appropriate permits and approvals.

“Sierra Pacific is energized about this opportunity to continue to provide quality, renewable wood products to meet the anticipated increased demand for housing and other societal needs,” comments Todd Payne, SPI President of Lumber. “This project will make our Eugene mill site one of the largest and most modern sawmills in the United States, continuing to build our momentum in growing our position in a critical market while maintaining our commitment to sustainably grown and manufactured wood products, and our talented, hard-working crew members.”

SPI acquired the Eugene site (formerly Seneca) as part of a larger 2021 acquisition and began plans for growth and expansion almost immediately. Construction of a new trucking facility and new engineering, technology and fabrication facility are underway, with completion expected this fall. These new facilities will expand efficiencies for the site and support the design, fabrication and construction of the new sawmills.

“These investment decisions by SPI are a reflection of our confidence in the need for sustainable building products, as well as that of our Oregon crew members and communities,” says SPI CEO Mark Emmerson. “We pride ourselves in our partnerships with our communities and the positive community impacts of our operations.”

Latest News

New Northwest Pellet Mill Gains Approval

New Northwest Pellet Mill Gains ApprovalAir quality officials recently issued a final notice and approval for an air quality permit at a new wood pellet manufacturing plant to be built by Pacific Northwest Renewable Energy (PNWRE) on a 60 acre site leased from the...

Collins Sues PG&E Over Dixie Fire

Collins Pine Co. and several affiliated companies have filed a lawsuit against Pacific Gas and Electric utility seeking compensation for property and business losses stemming from the Dixie Fire in July 2021, which was caused by PG&E’s equipment and negligent operations, according to the complaint.

Prairie Wood Products Closes Due To FS Transport Grant Dispute

Prairie Wood Products Closes Due To FS Transport Grant DisputeClaiming that a change in policy concerning the use of Forest Service grant money for transportation costs, Prairie Wood Products in Prairie City, Ore. suspended operations in March citing a disagreement...

Two Rivers Lumber Plans Second Alabama Mill

Two Rivers Lumber Plans Second Alabama MillTwo Rivers Lumber Co. plans to invest $115 million to build a state-of-the-art sawmill in Coosa County as the company’s second operation in Alabama. Demopolis-based Two Rivers Lumber has committed to creating 130 jobs at the...

C&D Lumber Announces Closure

C&D Lumber Announces ClosureOfficials with C&D Lumber in Riddle, Ore. recently announced the closure of the mill as of May 2, becoming the fourth sawmill in western Oregon to announce a closure since the start of the year. A reduced crew will work to run the...

Southern Cypress Manufacturers Assn. Elects 2024 Officers

Southern Cypress Manufacturers Assn. Elects 2024 Officers Members of the Southern Cypress Manufacturers Assn. (SCMA) elected officers for 2024 at the association’s Annual Meeting on March 25, in Charleston, South Carolina. Truss Beasley of Beasley Forest Products...

Find Us On Social

Newsletter

The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.

 

Subscribe/Renew

Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative.