California’s Big Creek Lumber Wary Of Growing Greenbelt
Anyone entering the mill at Big Creek Lumber, south of Pescadero, is immediately hit by a sensory overload — a cacophony of saws, the rattle of conveyor belts and a prominent pine fragrance. A freshly cut redwood enters the mill and, in a flurry of cuts, the tree is julienned into a pile of boards with some leftover scraps for potting soil.
About 100,000 board feet of timber are churned out of the lumberyard each day — or about enough wood to extend a single two-by-four about 21 miles. All those redwoods are chopped down from the verdant coastal forests from Half Moon Bay south to San Luis Obispo.
The trees are abundant, and demand is nearly endless, but Big Creek officials fear for the company’s future nonetheless. Here on the Peninsula, Big Creek controls the last remaining mill, giving them, in some ways, a local monopoly on lumber production. But company officials refer to that privilege as more like being the last dinosaur.
Over recent years, the lumber company officials say they’ve watched as thousands of acres of coastal hills have been “locked up” through conservation acquisitions and easements. The lumber company is not celebrating a new $300 million Measure AA bond approved by voters earlier this month to expand and maintain protected wilderness under the Midpeninsula Regional Open Space District. Big Creek officials fear the new pool of money could put the remaining open timberlands in the crosshairs of an expanding greenbelt up the Santa Cruz Mountains.
Back in 1980, California was self-sufficient for its lumber products, pointed out Big Creek spokesman Bob Berlage. But today more than 80 percent of the wood is brought in from out of state, mostly from Canada. The net effect, he says, is that Californians are tightening control of local resources and outsourcing the ecological damage elsewhere.
From the Half Moon Bay Review: hmbreview.com.
Latest News
U.S. Housing Starts Rebound In February
U.S. housing starts brushed off a sluggish January and reached a seasonally adjusted rate of 1.45 million in February, up 9.8% over January. Single-family starts were 830,000, a percent above January, while multi-family (five units or more) were at 608,000, up a whopping 24% over January. The uptick in February broke a four-consecutive monthly decline for the combined starts…
Cooper Machine Partners With EWD
Cooper Machine Co., a long-established manufacturer of quality sawmill equipment located in Wadley, Ga., announced that it is partnering with German-based sawmill machine manufacturer EWD Sagetechnik. Cooper Machine has been offering equipment for sawmill, pallet, and post and pole mills since 1965. The company is in its third generation of successful management…
Canfor DeRidder Has Log Cranes In Place
Fulghum Industries, Inc. reports the commission of two recently installed 170 ft. 45-ton log cranes for Canfor. The cranes will be feeding the new $160 million sawmill at DeRidder, La…
New Pellet Mill Entices Area Sawmills
Some Georgia sawmills will have a new market for their byproducts as Spectrum Energy Georgia LLC plans to begin construction this summer of the largest industrial wood pellet facility in the world at Adel, Ga. and expects to commission the plant 12 months later, or summer of 2024. The plant will operate at the site of an idled particleboard facility. The plant will have the ability to receive and process all forms of biomass, including sawmill residues (chips, sawdust and shavings), pulpwood, top wood, and in-woods chips…
Find Us On Social
Newsletter
The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.
Subscribe/Renew
Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.