Auburn, U.S. Air Force Developing Mass Timber Military Housing Prototypes
Auburn University engineers are working with the U.S. Air Force to redesign deployable military housing using mass timber, with the goal of creating temporary barracks-style structures that can be assembled faster and perform better in cold-weather environments.
Led by Auburn Engineering, the project combines structural design, materials testing and prototype development with architecture and building science expertise from Auburn’s College of Architecture, Design and Construction. Battelle is partnering with the Air Force to build prototypes.
David Roueche, the Gottlieb Associate Professor in the Department of Civil and Environmental Engineering says the Air Force needs temporary housing that can be transported, assembled and occupied quickly. Mass timber gives the team a way to meet that need by shifting more work into prefabrication, reducing on-site assembly time and improving thermal performance for cold-weather deployments.
Existing light wood-frame versions can require four or five people working eight- to 10-hour days over four or five days to build one structure—roughly 160 to 200 person-hours, Roueche says.
One of the central engineering challenges is finding the right balance between strength, efficiency and deployability. The structures must be durable enough for demanding environments without being overbuilt or difficult to transport.
That has required researchers to look beyond simply replacing conventional framing with mass timber. Standard cross-laminated timber (CLT) may be stronger and thicker than needed for this type of deployable structure, Roueche adds.
“Standard CLT is almost overkill for this application,” Roueche says. “It provides more strength than we need, so part of the challenge is figuring out how to use mass timber more efficiently.”
The team is evaluating designs intended to improve structural performance while also protecting insulation inside the assembly, an important consideration for cold-weather use. Testing in Auburn’s Advanced Structural Engineering Laboratory will help researchers verify the strength, stiffness and overall behavior of those designs.
According to Jake Elbrecht, assistant research professor in the McWhorter School of Building Science, a unique challenge in designing and constructing temporary housing is what happens at its end-of-life: “Air Force operations demand flexibility, and fixed housing impedes future redeployment. Designing temporary housing for disassembly and reuse accelerates redeployment and reduces long-term cost. Investigating structural performance, thermal performance and component reuse together reveals how these priorities compete and are weighed against one another in design decisions.”
Latest News
Fire Tragedy Strikes Robbins Lumber In Maine
On May 15, a fire and explosion in the silo area had turned Robbins Lumber in Searsmont into a scene of tragedy. It killed one 27-year-old fireman, injured eight firefighters and first responders, sent co-owners…
Wood Bioenergy Conference Proves Forest Residues Can Find New Life
Atlanta, Goergia The unstated message of the recent Wood Bioenergy Conference & Expo was to “turn lemons into lemonade,” with lemons being the crash of a significant portion of the pulp and paper industry and…
Forest Service Moves Forward With Disaster Recovery
The U.S. Forest Service announced that significant recovery efforts across national forests and grasslands continue to progress following damage caused over three years of natural disasters, including hurricanes, wildfires and flooding. These efforts were made…
Comact Releases New Generation Of Miller Planers
Comact, a global leader in high-performance OEM wood-processing technologies, has announced the new generation of the Miller planer. Building on decades of proven performance, this redesign introduces targeted improvements to support product quality, operational reliability,…
Find Us On Social
Newsletter
The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.
Subscribe/Renew
Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.