Sierra Pacific Industries Announces New Sawmills
Sierra Pacific Industries (SPI) plans to build a new sawmill complex, including two new sawmills located adjacent each other on the east side of its existing site in Eugene, Ore., eventually operating under one roof and ultimately replacing the existing sawmilling facilities.
The two sawmills will include a stud mill, patterned after SPI’s mill in Shelton, Wash. and consuming logs 5-16 in. diameter, and a cutting mill (large log mill) that will process logs 16 in. and larger.
The log mix will be similar to the current mix; however, the cutting mill is designed to extract greater value from each log, including dimension lumber, rough and surfaced timbers, shop, VG, clears, etc.—designed similarly to SPI’s four cutting mills in California.
The location allows SPI to complete the construction off-line while continuing to run its three existing facilities and maintain full employment of more than 300, before moving into the new facilities as they are completed.
The new sawmill complex will become one of the largest single site lumber producers in the U.S with an annual production capacity of 650MMBF, compared with the existing capacity at Eugene of more than 350MMBF.
The new sawmill project timeline anticipates completion between 2025 and 2026, contingent on securing appropriate permits and approvals.
“Sierra Pacific is energized about this opportunity to continue to provide quality, renewable wood products to meet the anticipated increased demand for housing and other societal needs,” comments Todd Payne, SPI President of Lumber. “This project will make our Eugene mill site one of the largest and most modern sawmills in the United States, continuing to build our momentum in growing our position in a critical market while maintaining our commitment to sustainably grown and manufactured wood products, and our talented, hard-working crew members.”
SPI acquired the Eugene site (formerly Seneca) as part of a larger 2021 acquisition and began plans for growth and expansion almost immediately. Construction of a new trucking facility and new engineering, technology and fabrication facility are underway, with completion expected this fall. These new facilities will expand efficiencies for the site and support the design, fabrication and construction of the new sawmills.
“These investment decisions by SPI are a reflection of our confidence in the need for sustainable building products, as well as that of our Oregon crew members and communities,” says SPI CEO Mark Emmerson. “We pride ourselves in our partnerships with our communities and the positive community impacts of our operations.”
Latest News
Lumber Prices On The Up As U.S. Home Sales Rise
It's not just a buoyant day for equities (China excluded) on Tuesday. Yes, lumber prices are on the up, too. News of a rise in new home sales in the US last month has helped push lumber prices up 2.5 percent to $246.10 per 1000 board feet, writes Mamta Badkar. And the...
Maley & Wertz Acquires Kirkham Hardwoods Inc.
Maley & Wertz Acquires Kirkham Hardwoods, Inc.Maley & Wertz Inc., an Evansville-based firm that acquires and sustains North American hardwoods, has acquired Kirkham Hardwoods Inc. According to a news release, the merger will better position the combined...
Some Hardwood Sawmills Struggle To Stay In The Black
Hardwood lumber sales remained relatively slow, as a combination of lackluster overseas demand and the easy availability of lumber kept many buyers on the sidelines. Many mills tell us that the high prices they paid for timber a few months ago make it very difficult...
Lumber Supplier Canfor Loans $30 Million To Conifex
Canfor and Conifex say an investment agreement between the two lumber producers for $30 million has been completed. The loan by Canfor to Conifex Inc., a wholly-owned subsidiary of Conifex Timber is for five years, with the proceeds to be used for general corporate...
World’s Tallest Wood Building Now Under Construction
Cross laminated timbers are being used in mass quantities for the tallest wood building so far: a 121-unit, 10-story apartment complex in London. Architects Waugh Thistleton, CLT engineers Ramboll and developer Regal Homes, says the most exciting aspect of the...
Conifex Timber Buying Shuttered G-P Sawmill In Arkansas
Conifex Timber Buying Shuttered G-P Sawmill In ArkansasConifex Timber Inc. of Vancouver, Canada, said Thursday that it is buying the former Georgia-Pacific sawmill south of El Dorado. The statement said Conifex has completed the purchase of the outstanding shares and...
Find Us On Social
Newsletter
The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.
Subscribe/Renew
Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.