New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Stimson Lumber Invests In Oregon Sawmill
Stimson Lumber Company recently invested $5.5 million for mechanical upgrades at its Tillamook, Ore. stud mill. An estimated 5%, or $275,000, was spent in Tillamook County on local contractors, helping to boost the local economy.…
Resilience Capital Partners Acquires PA Sawmill
Resilience Capital Partners, a Cleveland-based private equity firm, recently announced the completion of the acquisition of Weaber, Inc., a leading hardwood lumber mill. Founded in 1941, Weaber, Inc. is one of the nation’s leading hardwood…
Low Country BioMass Pellet Plant Utilizing Sawmill Residue
googletag.cmd.push(function() { googletag.display(‘div-gpt-ad-1548381510056-0’); }); Low Country BioMass, LLC, Ridgeland, SC, completed construction and began production in mid-November. The pellet plant is on track to finish the commissioning process and begin its 24/7 schedule by the…
Mississippi Lumber Company Forced To Shut Down
Hankins Lumber Company in Elliott, Miss. announced last week that it would temporarily cease operations beginning January 6. According to Office Manager Jerry Pegg, employees were told that operations will be suspended until the lumber…
Find Us On Social
Newsletter
The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.
Subscribe/Renew
Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.