Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Margin of Error Is Pollster’s Safe Haven
Story by Rich Donnell, Editor-in-Chief I am sure you’ll notice in this issue our extensive coverage of our annual Sawmill Capital Expenditure Survey. The articles run from page 8 to page 34, so basically that…
Sawdust Samples Sent To U.S. To Help Determine Cause Of B.C. Mill Explosions
WorkSafeBC officials say they are still trying to determine the cause of fatal blast that leveled the Burns Lake sawmill in January, including what role sawdust may have had in the explosion that killed two…
Everett Pulp Mill To Be Demolished
Kimberly-Clark said Thursday it plans to demolish its closed pulp-and-paper mill on Everett’s waterfront and sell the 66-acre property. The company laid off 760 employees before shutting down the roughly 80-year-old plant earlier this month.…
Sawdust Ordered Removed From B.C. Mills
In an unprecedented, precautionary crackdown, safety officials are ordering every sawmill in British Columbia to remove all accumulated sawdust from their premises, a factor cited as a possible trigger of two catastrophic mill explosions in…
Find Us On Social
Newsletter
The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.
Subscribe/Renew
Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.