Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
J.D. Irving Sawmills Division Invests To Open Maine Sawmill, Creating 60 Jobs
J.D. Irving, Limited Sawmills Division announced today that it will invest $30 million in a new state-of-the-art softwood sawmill at Ashland (Nashville Plantation), Maine. During the construction phase, the new facility will employ up to…
Stella-Jones Invests As Wood Products Sales Rise
Stella-Jones Inc. says its pressure treated wood products sales rose 34% during the second quarter, as demand for utility poles and railroad ties were buoyed by the general economic recovery. Integration of the recently acquired…
Greenpeace Canada Fights Back Against Resolute Forest Products Lawsuit
A Superior Court judge in Thunder Bay is reserving his ruling in the first battle of what is expected to be a long courtroom war between Resolute Forest Products and Greenpeace Canada. The forestry giant…
Find Us On Social
Newsletter
The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.
Subscribe/Renew
Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative.