Labor, Materials Issues Cause Project Delays

The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.

In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.

The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.

Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.

Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.

According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.

Latest News

Ransford Automates Post-Pointing Line

Charles Ransford & Son is a producer of British timber products operating on a 38 acre site at Bishops Castle in Shropshire, with fencing and landscaping products represent the lion’s share of its production. The 55 employees work on a single shift, dealing predominantly with redwood.

Robbins Lumber Lists Hancock Sawmill Site For Sale

Robbins Lumber has listed its 100-acre sawmill complex in Hancock, Maine for sale with a price of $2.5 million. This site was acquired from Pleasant River Lumber in 2023 by Robbins. Included in the property sale are kilns, a planer mill, truck scale and a 42,000 sq. ft. sawmill with an attached machine shop. The property also includes a fully leased apartment building.

Roseburg Names Orozco To Direct Strategic Business

Roseburg has annouced that Nadine Orozco has been promoted to Director of Strategic Business Development. She has served as manager of strategic business development since 2022, and has been deeply involved in key company projects, including the recent sale of Roseburg’s Simsboro, La., particleboard plant to Kronospan and the company’s historic $700 million investment in Oregon manufacturing.

Find Us On Social

Newsletter

The monthly Timber Processing Industry Newsletter reaches over 4,000 mill owners and supervisors.

 

Subscribe/Renew

Timber Processing is delivered 10 times per year to subscribers who represent sawmill ownership, management and supervisory personnel and corporate executives. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative.